Friday, December 28, 2007

Now that's what I'm talking about

Can't wait to have a party now!

What's left: some electrical fixture installation, install the cabinet doors, some door and closet painting, speaker install, and approx 1,000,000 little details.

-DT

Sent via BlackBerry by AT&T

Not sure but something does not look quite right

Are they supposed to be installed this way!

:-)

-DT

Sent via BlackBerry by AT&T

Furniture delivery is underway

Have waited a long time for this. Soon I will have a place to sit in the new room!

-DT

Sent via BlackBerry by AT&T

Thursday, December 20, 2007

Fridge is in!

After five attempts - fridge number six is installed and looking good.

-DT


-DT

Thursday, December 06, 2007

More trim and stove backsplash

Yesterday the backsplash was installed behind the stove. Grout is not in yet. We think it turned out pretty cool. Electrician starting to install fixtures and finish the wiring too. The construction/finish part should be done this week or early next week. We hope. Then the painter starts for final color application.

-DT


-DT

Monday, December 03, 2007

Ovens today

The ovens were set today - not wired in yet.

-DT


-DT

Mud room tile

Monday - tile set in the mud room.

-DT


-DT